Zone 2 HVAC package for the Forel / Baronang FPSO
Medco E&P Natuna
Goal
A Zone 2 compliant HVAC unit with a high external static pressure.
Challenges
- The approved manufacturer list was mostly commercial brands not designed for hazardous areas.
- International hazardous-area HVAC makers quoted long lead times.
Approach
- Engineer-to-order design with equivalent Ex components meeting the project specification and schedule.
- Dampers, ducting and coalescer filters made in-house to shorten lead time.
- Procurement sequenced on drawing approval; bi-weekly progress meetings with a dedicated project engineer.