Zone 2 HVAC package for the Forel / Baronang FPSO
E&P · Delivered in 22 weeks

Zone 2 HVAC package for the Forel / Baronang FPSO

Medco E&P Natuna

Goal

A Zone 2 compliant HVAC unit with a high external static pressure.

Challenges

  • The approved manufacturer list was mostly commercial brands not designed for hazardous areas.
  • International hazardous-area HVAC makers quoted long lead times.

Approach

  • Engineer-to-order design with equivalent Ex components meeting the project specification and schedule.
  • Dampers, ducting and coalescer filters made in-house to shorten lead time.
  • Procurement sequenced on drawing approval; bi-weekly progress meetings with a dedicated project engineer.
Zone 2 dampers and ducting for BP's waste treatment facility
E&P · Delivered in 12 weeks

Zone 2 dampers and ducting for BP's waste treatment facility

BP Berau Ltd.

Goal

Zone 2 fire dampers, blast dampers, ducting and instrumentation for an E&I room.

Challenges

  • Items required within two months.
  • No Zone 2 damper manufacturer could deliver in that time.

Approach

  • Staged partial deliveries agreed with the client.
  • Long-term actuator supplier relationships cut lead time from 14 to 6 weeks.
  • Weekly planning meetings with the client.
Offshore condenser fan repair under a maintenance contract
M&S · Replacement dispatched in 3 days

Offshore condenser fan repair under a maintenance contract

Offshore production platform

Goal

A damaged condenser fan blade on an offshore HVAC unit.

Challenges

  • No spare on site for in-situ replacement.
  • Long lead time for a new OEM blade.

Approach

  • Direct line between the offshore crew and our workshop engineers.
  • A stock blade re-engineered to the specification; airflow verified on our blower test bench.
  • Replacement dispatched from our warehouse within three days.
Ex motors rescued at pre-commissioning
ROR · Ready for site in 8 days

Ex motors rescued at pre-commissioning

Hazardous-area HVAC package

Goal

Ex motors showed low insulation resistance during pre-commissioning – a sign of moisture ingress.

Challenges

  • Repair on site could void the warranty or compromise the type of protection.
  • New motors were costly with a long lead time.

Approach

  • Motors sent straight to our IECEx Certified Service Facility.
  • Repaired to IEC 60079-19 with full as-found / as-left documentation.
  • Inspected, tested and ready for reinstallation within eight days.

Maintenance & service

Maintenance contracts

ClientPeriodScope
Medco E&P Natuna2024–2027Offshore HVAC-R maintenance contract
PT Mitra Energi Pelayaran2025–2027Marine HVAC-R maintenance contract
Pertamina EP CepuCurrentHVAC maintenance contract
Pertamina Hulu Energy WMO2021–2025HVAC maintenance contract – CPP1 & CPP2; ORF Gresik, Poleng & PHE-5
Eni Muara Bakau2021–2024HVAC maintenance contract – Jangkrik FPU & onshore receiving facility
Pearl Oil (Mubadala Energy)2020–2023HVAC maintenance contract – Ruby site & process-quarters platform
Premier Oil Natuna Sea (Harbour Energy)2016–2025HVAC maintenance, modification and replacement – Anoa FPSO, Anoa, AGX & Gajah Baru platforms
ExxonMobil Cepu2015–2021HVAC maintenance contract
ConocoPhillips Indonesia2010–2015HVAC maintenance contract

Engineering & production

Engineering projects

Client / projectScopeYear
Medco E&P – Forel FPSO (via Multipanel Intermitra)Zone 2 T3 IIA rooftop unit: 550,000 Btu/h, 15,600 cfm at 1,500 Pa, Heresite-coated coils, SS316L casing2022
Pertamina Hulu Energi WMO – living quartersHVAC replacement: 102 kW packaged unit, Heresite coating, SS316L – engineering to commissioning2022–2023
Pertamina Hulu Kalimantan TimurClass 1 Div 2 packaged HVAC, 2 × 100,000 Btu/h with room-pressure control (25–50 Pa); pressurising system2022–2023
Premier Oil – Gajah Baru CPPExhaust-air duct and compressor services; local content 65.1 % verified by Surveyor Indonesia2024–2025
Premier Oil – Anoa FPSOTR pressurisation: 4,000 m³/h, chemical H2S filtration to 10 ppm, ATEX gas-detection control panel, FAT and commissioning2019
ExxonMobil Cepu – FSO Gagak Rimang (PB12)162 m ducting reconstruction, HVAC unit upgrades and a new 530,000 Btu/h Zone 2 unit with PLC control2019–2020
PHE ONWJ (via Timas Suplindo)PLC-integrated redundant HVAC system up to 850,000 Btu/h2019–2020
PHE ONWJ – Zulu platformAHU replacement (2 × 300,000 Btu/h); split units and pressurising unit replacement2013 & 2018
BP TangguhHVAC for the LCR expansion; E-house HVAC2018–2021
Medco E&P Natuna – Marlin NatunaHVAC package installation for the ECR; PLC HVAC modification for the LQ2025
Premier Oil Natuna SeaTemporary refuge system and HVAC unit fabrication / replacement2016–2023

Clients

Who we work with

Client logos

Beyond oil & gas, our chillers, cooling towers, cold rooms and grain-cooling units have served Soekarno-Hatta airport terminal areas, the Indonesia Air Show, Danone, Unilever, Cargill, Greenfields, Darya Varia, Sinar Oleochemical, Asahimas Chemical (AGC), Synthetic Rubber Indonesia, Sulfindo Adiusaha, Petnesia Resindo, Sequis Center Jakarta, Blue Bird and BULOG grain stores in Subang, Kendal and Sragen.

Tell us about your site

Share the area classification, duty and schedule – an engineer replies within one working day.

Email sales@eskimo.co.id WhatsApp +62 813-1931-1988